Team numbers were somewhat down on Monday's numbers, however, three main areas were tackled.

Firstly, the diesel tanks received their second and third coats of paint.  The final colour is white, not all of this was completed.  They are looking really splendid now.
Another tank, has found a 'repurposing'.  The old hydraulic oil tank from inside No.5 has been earmarked to act as a containment around the control block manifold just in case there are any leaks of oil which can be just a drip or a high pressure spurt.  Some internal modifications need to be made, but it will perform the function well.
At the rear of No.5, the current hydraulic oil tank has been released from its fixings and is now ready to lift out.  We are looking to relocate that in a better position, clearing away one of the big trip hazards on the deck.
The afternoon saw us attending to the turret ring broken bolts.  Four of them sit buried in their threads.  A process of drilling and then re-tapping seems to work.  So far we have dealt with two and started on the third.  Once complete, we can devise a way to replace the turret back on the boat - it is heavy.

When all the major components are around us, including the engine, we will gather them together and contemplate the positioning of them within the hull.  A good day's effort. 

08 January 2019

Ham Mill update Mon Jan 7th 2019

by: Andy P.

What a busy start to the New Year.  Following an update meeting at the depot a gang of people descended on Dock Lock and returned with the 4 x 6m lengths of pipe. 3 were loaded and roped for their trip to Ham Mill and a curious site it all made. WD rocket launcher was heard as a description.

Lots of activity. Cars were parked all the way down the roadway as there were so many people.
Pipes were unloaded and the remaining bends checked to see if we can get down the concreted tow path. We can but need a towpath bypass building first.
Bob, back onto bricking up the overflow inlet-a slow job still, due to all the cutting and crazy angles.
Welcomed guest appearances from Ron and Harry and with Digger Duncan, enabled the mini digger, big digger and dumper to be brought into use. Clearing the yard of its glutinous top structure which was quite capable of swallowing volunteers, tidying up the off side bank, extending the yard entrance now it had been semi cleared. The big digger was used to try to lift out the tree stump which is in the way. Tree stump 1, Digger 0.

2 Fence posts were fitted to allow the end of the bridge to be fenced off at some point.  
Mixer Mathew, Monday Maurice, Calibration Kay were joined by Richard and set about bringing the trees, shrubs and cuttings, down to the slope from the garden. They were carefully placed before being beautifully planted in a very pleasing and satisfactory manor-it looks really nice.


07 January 2019

Western Depot - Back at work

This morning. the support structures in our 'Carnival' facilities caravan were placed under considerable strain as many of the teams, normally working out on the canal descended on Eastington to listen to Reg's state of the nation address to kick off the new year.  Some 40 volunteers were present.  
 
Getting the information quickly to the Eastern End guys also seemed to have been taken care of with this prototype rocket launcher positioned in the yard pointing roughly in the right direction!

The Ryeford to Oil Mills Pound

by: Bob H.

After a long Christmas Break, the Wet dredging team started up again to continue clearing the accumulated silt and old tip material from the Ryeford to Oil Mills pound.
Dredger Patricia is now in the process of gaining full release from her trials.


This has taken longer than we would have liked, but doesn’t everything?
Today after the Tug Team bought along a hopper for us, we carefully manoeuvred Pat to a position where we could more easily get at the mud, settled in the spud legs and began dredging.
With Bob H. the instructor in charge, Richard F underwent a long stretch at the controls.
He looked quite pleased and proud after his spell at the levers (and so he should!). 

The result of his Richard’s efforts are in the hopper alongside. Please note, most of the water was already in there, we’ll pump it out when the hopper is nearer to full. 
A lot of people think that all we do is to sit in the seat and pull or twiddle levers. Far from it! Dredging is an involved series of activities. The range from deciding where to dredge, how and where to dispose of the muck (with all it’s regulations), maintenance of the plant, learning how to operate the plant and the qualifications required. We also require knowledge of Invasive Non Native Species, fish and wildlife protection requirements and their controls.

Above all this is the fundamental requirement of safety of the Volunteers and Public.

"May all your combined leaks never exceed your bilge pump capacity.
Project 'DNF' - No.5 Refit

by: Vince H.

I had a surprise last Wednesday when Peter said "I may not be there on Monday, so you are in charge". Gulp... Err... Management... How hard can it be?

The plan was to continue the clean out of the bilges and perhaps take out the old hydraulic tank that was mounted midships.  Now it is the nature of these things that you can never remove one item without taking out several other things and pretty soon the cabin floor and its bearers had been removed to allow the tank to be turned through ninety degrees and tipped over.

The resulting space allowed us to get in and review the vast array of hydraulic plumbing lurking under the side decks. Much time was spent tracing pipes and trying to remember which ones had been disconnected from the control block and work out those that had been unused for many years with the various changes in the dredger's configuration over its life.  In the end, most of the plumbing was removed with only two feed pipes left in place, though their future is also in doubt depending on where all the components are mounted.

Meanwhile in the yard, John and Gill were reclaiming the unused fuel tanks, cleaning the insides and painting the outside in red oxide.
In the workshop, Ken produced a bush that will allow us to accurately drill out the sheared bolts in the slew ring of the dredger's boom.  A task for Wednesday.
With time left over all the remaining wiring was removed.  Most of this will be replaced with a new loom that comes with the engine.

04 January 2019

SVCC launches a new web site

by: Peter B.


Come and visit SVCC’s new web site at www.stroudvalleyscanal.co.uk and see how the canal is being presented to the world at large.  

This will be the new site where all of the latest news and information about the canal can be found. It has details of news, stoppages, details on canal assets and is also where you will be able to find out how to apply for moorings or licences.  It has been produced by Mark Strange, a long-time volunteer on the Eastern section and Peter Best and it went live in early December.  It is now THE place where any issues or closures will be published.


03 January 2019

SVCC introduces a new Facilities Guide to the Cotswold Canal.

by: Peter B.

A new guide to the canal covering the stretch from Pike Lock, Eastington to Brimscombe has been published on-line.  


It is intended for all users of the canal be they on the water or just walking.  It has been produced by David Jowett, the brilliant editor of the TROW and SVCC’s Chairman, Peter Best and will be updated quarterly, coming out on the 1st March, 1st June, 1st September and finally on the 1st December. 

It hopes to be a pretty comprehensive guide to what’s happening on the canal, how to use it, the current limits of navigation and what facilities the canal and the surrounding area can offer a visitor.
Later on in the year, we will start actively promoting the canal as being ‘open’ to trail boaters and other water bound users.

Comments and up-dates are welcome! Please send any revisions to peterbest(at)spslimited(dot)co(dot)uk   <anti spam format...ed>