Project 'DNF' - No.5 Refit
A much smaller team yesterday, but progress made. We worked mainly on the decking plates, drilling and preparing them for painting. Marking out the holes had to be done from underneath and the method used was to place the plate, spray each of the holes and then use a 10mm drill to spot the centres.
This worked well and all the bolts dropped through. Painting has now commenced, once complete, we can seal and bolt down.
In the ever active paint shop, more component parts received another layer or two. We had hoped to fit the new pinion - but, just where did that safely stored key go?
07 February 2019
05 February 2019
The Canal IS Level.
by: Bob H.
Well, it may be so on the surface, but like the Duck on a fast-flowing stream, all is far from calm and level underneath.
One of our problems is that we don’t really know where the really shallow bits are or what volume of silt we have to remove. Enter a nifty bit of high tech kit.
Plotted and stored on the laptop, later analysis provides a detailed canal bed contour map and, based on a specified channel section, how much silt we need to remove by dredging.
Did I mention that it’s quick too?
Today, Mark (LSS), assisted by Bob and Alex (CCT dredging team) did a first pass of the survey from Wallbridge to Ryeford Top Lock. The little boat covered about 20km and made over 40,000 measurements of depth, on about 3km of canal.
Tomorrow we do a bit of follow-up on sections where trees stop the gps or the mobile signal don’t work because of overhanging trees and mobile dead spots. Thank you all boat crews and dredgers for suspending work tomorrow for a day (silt free water is needed). We’ll report later on the findings.
"May all your combined leaks never exceed your bilge pump capacity.
by: Bob H.
Well, it may be so on the surface, but like the Duck on a fast-flowing stream, all is far from calm and level underneath.
Many of us know only too well that there are sections of the Canal which are quite shallow - we on the dredging team (Wet and dry) are working hard to remedy that. We are removing quite large volumes of silt and other debris to restore the level to around 1.5 metres in the main channel, with deep enough edges to get to the banks.
We found a very helpful company, Land and Satellite Services,
who have equipment which measures quite accurately the water depth and the precise locations of all the pesky shallow bits. Accurate to 2mm anyway!!
All the measurements are done without anyone getting in a boat, pontoon or coracle. It’s all done from the bank with a radio-controlled boat, gps, laptop and a live connection to bang up to date Ordnance Survey data. Depth is taken every 1/2 metre or so the boat travels.
Did I mention that it’s quick too?
Tomorrow we do a bit of follow-up on sections where trees stop the gps or the mobile signal don’t work because of overhanging trees and mobile dead spots. Thank you all boat crews and dredgers for suspending work tomorrow for a day (silt free water is needed). We’ll report later on the findings.
There's a hole in Delilah, Delilah, Delilah, …
The next bit took a while ... but now we have a much bigger hole. The ladder has moved, too, and will later need fixing in a new position. By now the pump had done its job, taking water levels down from about 18 inches to 3 - so it had been moved and started work removing the rain and snow melt from the main hold.
Folks aren't meant to clamber over our vessels: we try to discourage them, but we're sure they do. We'd hate someone to fall in, so after tidying up the edges, we put a temporary cover over the hole.
Next task is to put edging round the hole, to stop rain dribbling in, and to provide extra strength (although judging from today, it seemed to have plenty already!).
by: Dave I.
Luckily, there's meant to be - but it is new.
You may recall that we recently hauled her all the way back to Griffin Mill Lock. This was so she could be near her sister (brother ???) barge, Samson and that's because Samson (and the piling team, of course) have what it takes to help do her conversion.
Here's what her deck looked light this morning. Pretty clear, apart from a battery and bilge pump (we knew we'd need them) and a few tools.
And here's what she looked like shortly afterwards. The hatch was open. The bilge pump was pumping - and did so for a fair while. The generator was getting ready to generate. And the angle grinder (spot the handle!) was getting ready to grind, although not around angles. The next bit took a while ... but now we have a much bigger hole. The ladder has moved, too, and will later need fixing in a new position. By now the pump had done its job, taking water levels down from about 18 inches to 3 - so it had been moved and started work removing the rain and snow melt from the main hold.
Folks aren't meant to clamber over our vessels: we try to discourage them, but we're sure they do. We'd hate someone to fall in, so after tidying up the edges, we put a temporary cover over the hole.
Next task is to put edging round the hole, to stop rain dribbling in, and to provide extra strength (although judging from today, it seemed to have plenty already!).
Why are we making holes, you may ask? For a crane in Delilah, Delilah, a crane.
The crane is already in WD, and is progressing well. There's still lots to do before the crane & Delilah meet. If you'd like to help, Dave & Myron would be interested in hearing from you: email dave(dot)irving(at)cotswoldcanals(dot)com and/or Myron(at)hamshill(dot)co(dot)uk <anti spam...ed>
Finally, don't forget to look at the background: the piling team are making great progress on the landing stage below Griffin Mill Lock.
Ham Mill 4th Feb 2019
by: Matthew J.
Our regular blogger Andy P. is taking a well-earned break this week, but it was still a good turn-out on Monday with Bob, Duncan, Maurice, Matthew, Jason and Kay turning up to do battle with the mud once again.
First job of the day was to complete the new temporary (2) towpath by levelling off the ground by the non-retaining wall and adding further temporary (11) trench boards to meet up with the temporary (9) trench boards laid last week. (See last week’s blog to make sense of this). A few unfortunate walkers who turned up in the middle of all this had to traverse some extremely temporary (12) arrangements to get through, but the final result didn’t look too bad.
by: Matthew J.
Our regular blogger Andy P. is taking a well-earned break this week, but it was still a good turn-out on Monday with Bob, Duncan, Maurice, Matthew, Jason and Kay turning up to do battle with the mud once again.
First job of the day was to complete the new temporary (2) towpath by levelling off the ground by the non-retaining wall and adding further temporary (11) trench boards to meet up with the temporary (9) trench boards laid last week. (See last week’s blog to make sense of this). A few unfortunate walkers who turned up in the middle of all this had to traverse some extremely temporary (12) arrangements to get through, but the final result didn’t look too bad.
Having finally got the towpath away from the line of the new bypass pipe, the rest of the day was spent on trench warfare, starting with the sloping path going down under the bridge.
An old gas pipe intruding through the side of the trench gave Bob an excuse to get the disc cutter out again and create another impressive shower of sparks.
Several hours later and after much digging, scraping and barrowing, we’d made a satisfyingly deep hole, and trudged home in our muddy boots content with another good days’ progress.
04 February 2019
A Window on the Canal
by: Bob H.
Our Patricia is currently both working hard with our dedicated dredging volunteers, in both dredging mode and being used as a classroom.
First time for a while this metal window frame has any light passed through it.
We are making steady progress as the existing operators get to grips with Patricia’s very different (to Dredger No. 5’s) characteristics.
Our numbers are at the moment somewhat depleted by a number of operators and trainees getting deeply involved with the massive refit job of Dredger No. 5 at the Western Depot. When SHE comes back into service, and familiarisation Training is completed, mud will be moved in vast quantities!
by: Bob H.
Our Patricia is currently both working hard with our dedicated dredging volunteers, in both dredging mode and being used as a classroom.
Today started off as normal with our access to her via the back garden of one of our fellow volunteers. We opened up, carried out pre-start checks, started the engine to warm through, turned on the gas and made a brew of tea or coffee. As we sipped, the engine warmed the hydraulic oil and cabins and the day’s programme was discussed, as was our developing training programme.
Then onto work. Dredging.
The empty hopper was pulled alongside and mud, silt and debris began emerging from the murky depths. The “Dry Boys” have reached well across the canal, so we “wet Boys” are completing what they can’t quite reach. A first! A window on the Bed of the canal.First time for a while this metal window frame has any light passed through it.
We are making steady progress as the existing operators get to grips with Patricia’s very different (to Dredger No. 5’s) characteristics.
As we dredged away, Ice Breaker Margaret very slowly came by thank you chaps). We felt a little sorry for them, so while we dredged, they moored alongside and we used our wonderful facilities for a brew for them too!
Project 'DNF' - No.5 Refit
A great team on board today, eight of us were working on the project for at least some of the time. Three main tasks were tackled, they were, the plating to cover large holes in the deck, the joystick support assembly and plenty of cleaning and painting of a number of components. Some time was also spent tightening the turret bolts with a torque wrench and preparation for welding the engine mounts down.
The tread plate for the deck arrived last week, the two cover sizes required happened to coincide with at lease a width or a length of a plate, so a single cut with the gas axe to each sheet produced both plates.
These were later placed on the deck and marked out for drilling as new low profile dome head fixings are to be used to secure them. There will be a large flat and safe area around the rear of the vessel to move around on. It was previously a myriad of trip hazards.
In the cab, the pivot holes for the joystick assembly were drilled and tapped. A small slotted bracket was then fabricated so that the forward latch position for when the operator accesses or departs the seat gives space to get their legs past easily. This component has how been sent to the painting department.
In the ever productive painting department much was going on, especially with preparation work to the engine cover where some redundant protruding components were removed and the old flaky paint stripped off. More paint was applied to the hydraulic tank and also to the engine cover side flaps. Next time should see red oxide paint on the deck plates once they are drilled.
Later in the afternoon, white van man dropped off the new pinion gear for the turret motor, also returning the worn one. This we can also install next time.
We were blessed with a warm and dry day, which always helps maximise progress. Well done everyone, do come again.
A great team on board today, eight of us were working on the project for at least some of the time. Three main tasks were tackled, they were, the plating to cover large holes in the deck, the joystick support assembly and plenty of cleaning and painting of a number of components. Some time was also spent tightening the turret bolts with a torque wrench and preparation for welding the engine mounts down.
The tread plate for the deck arrived last week, the two cover sizes required happened to coincide with at lease a width or a length of a plate, so a single cut with the gas axe to each sheet produced both plates.
These were later placed on the deck and marked out for drilling as new low profile dome head fixings are to be used to secure them. There will be a large flat and safe area around the rear of the vessel to move around on. It was previously a myriad of trip hazards.
In the cab, the pivot holes for the joystick assembly were drilled and tapped. A small slotted bracket was then fabricated so that the forward latch position for when the operator accesses or departs the seat gives space to get their legs past easily. This component has how been sent to the painting department.
In the ever productive painting department much was going on, especially with preparation work to the engine cover where some redundant protruding components were removed and the old flaky paint stripped off. More paint was applied to the hydraulic tank and also to the engine cover side flaps. Next time should see red oxide paint on the deck plates once they are drilled.
Later in the afternoon, white van man dropped off the new pinion gear for the turret motor, also returning the worn one. This we can also install next time.
We were blessed with a warm and dry day, which always helps maximise progress. Well done everyone, do come again.
01 February 2019
Wheels, Wheels My Depot for Some Wheels!
By: Buffs
On Monday Western Depot bid farewell to our trusted transit van as it went to a place of rest and quiet. On Wednesday we were deluged with transport requests. Collect an engine from Upton, collect steel plates from Gloucester, replace an information board at Griffin’s Mill, deliver finished logs and collect more cut logs on the way back(twice) and return the digger and borrowed kit to the lenders. And all the vehicles were frosted heavily, one so badly the doors would not open until the ice was melted with a heater.
And before we could move anything the new engine for dredger No5 had to be offloaded and swung into place. (More on this elsewhere in the blog).
The benches team of Mike, Will, Richard and Maurice had the early morning pleasure of fitting the tools and materials, fully assembled bench and information board on its 5 foot long legs into the Mitzi loading bay and securing it. The legs of the information board are so long because of the depth to which they are set into the ground. Mike’s expectation of breaking through frost hardened ground was confounded with the first strike as the spade sank easily into the ground. The sign board adds background to the memorial plaque Pvt. Howard Pegler set into the bench. To read more of Pvt Pegler’s bravery and enjoy the bench enjoy the towpath walk along this recently dredged stretch of the T&S canal.
Meanwhile the thinly populated yard echoed to the ring of hammers and the electric chatter of the welder as the metal work for the new dredger engine was fabricated.
The crew of Wooky Hole , one of our workboats are based at WD. They carry out weed and reed removal and generally tidy the waterside environment of the cut. Over the last couple of weeks they have been bramble bashing at Harper’s field landing stage to great effect. The visual benefit is quite stark even though the job is not complete yet. One job that can only be done from the water is maintaining a clear air draft over the water to allow safe passage of boats and boaters along the canal. This is done with loppers, pole saws and, when necessary, chainsaws. To reduce the frequency of lopping the roof of the cabin has been (first) fitted with a collapsible handrail made at WD and fitted this week. The rail must be collapsible to allow the boat to pass under our bridges. All that remains is for the final adjustments to be made and painting to be completed and Mike W can tick off another Job.
As to the replacement van- we have been promised it ‘soon’. On Wednesday’s efforts ‘soon’ can’t be soon enough!
By: Buffs
On Monday Western Depot bid farewell to our trusted transit van as it went to a place of rest and quiet. On Wednesday we were deluged with transport requests. Collect an engine from Upton, collect steel plates from Gloucester, replace an information board at Griffin’s Mill, deliver finished logs and collect more cut logs on the way back(twice) and return the digger and borrowed kit to the lenders. And all the vehicles were frosted heavily, one so badly the doors would not open until the ice was melted with a heater.
And before we could move anything the new engine for dredger No5 had to be offloaded and swung into place. (More on this elsewhere in the blog).
The benches team of Mike, Will, Richard and Maurice had the early morning pleasure of fitting the tools and materials, fully assembled bench and information board on its 5 foot long legs into the Mitzi loading bay and securing it. The legs of the information board are so long because of the depth to which they are set into the ground. Mike’s expectation of breaking through frost hardened ground was confounded with the first strike as the spade sank easily into the ground. The sign board adds background to the memorial plaque Pvt. Howard Pegler set into the bench. To read more of Pvt Pegler’s bravery and enjoy the bench enjoy the towpath walk along this recently dredged stretch of the T&S canal.
Meanwhile the thinly populated yard echoed to the ring of hammers and the electric chatter of the welder as the metal work for the new dredger engine was fabricated.
The crew of Wooky Hole , one of our workboats are based at WD. They carry out weed and reed removal and generally tidy the waterside environment of the cut. Over the last couple of weeks they have been bramble bashing at Harper’s field landing stage to great effect. The visual benefit is quite stark even though the job is not complete yet. One job that can only be done from the water is maintaining a clear air draft over the water to allow safe passage of boats and boaters along the canal. This is done with loppers, pole saws and, when necessary, chainsaws. To reduce the frequency of lopping the roof of the cabin has been (first) fitted with a collapsible handrail made at WD and fitted this week. The rail must be collapsible to allow the boat to pass under our bridges. All that remains is for the final adjustments to be made and painting to be completed and Mike W can tick off another Job.
As to the replacement van- we have been promised it ‘soon’. On Wednesday’s efforts ‘soon’ can’t be soon enough!