The WRGies @ Dock Lock update Steady progress has been made on the two main tasks at Dock Lock. Firstly, the steps at the western end are almost up to the top and I'm assured that they have every intention of going round the bend soon!
At the eastern end, the spill weir construction has really advanced. Th concrete base was poured as planned on Wednesday and now the reinforced block work is well underway. Their camp ends today, so further progress at this site will be noticeable by the colour of the hard hats changing from mostly red to green.
A few words from the DofE Award students informed me that whilst it had been hard work, they had enjoyed their time with the gang, especially meeting folk from all walks of life.