17 August 2018

Pat's Progressed

by: Bob H.

Since the original team leader has only just returned from R&R (don’t mention it took 12 weeks!) and the approved stand-in decided it was his turn to go AWOL, minor but significant jobs are being attended to. 

 This week we have cleaned out the fuel agglomerator bowl (again) and having got oily hands, ran the engine to get hot water to wash hands - what a wonderful improvement on the coal stove, kettle and bunker! 

  Later, having found the keys, obtained flexible pipework and a full bottle of gas, the gas cooker installation was tested and found to operate perfectly!