by: Andy P.
Nov 2017 the vacuum pipework was completed and commissioned.
It did not last long and despite numerous folks and numerous methods, the
vacuum failed to work for a sufficient length of time to get the water from the
pond up and into the canal. So Bob, Mathew, Maurice and Andy P returned. First
job was to close the inlet valve by the pond, which when we left in May 2018
moved easily with 1 hand. Not this time, 4 hands, on our stomachs, a hammer and
40 mins later it was closed. Can WD engineering make a frame at waist level to
make it easy to open and close-Thank you.
The pipework which took days to assemble yielded in 30
mins-the saw did help a lot. Then digging and much more digging to drop the
level and straighten the run across the tow path.Off to Brimscombe to take the old pipes and look at the shiny new, very, very heavy pipes and fittings. Well, a bit of a jigsaw but eventually figured out how it all might work. John B was not too impressed about his order and drawings versus what was delivered. More bits needed. A very pleasant lunch break and WRG flapjack, at the bookshop, did help.
Then back to digging in between rain showers.
Weds was more digging. Lots of digging. Collected 2 bends
and used them to work out the best way to get across the towpath, with one
being cut to size to make the correct angle. Back to the bookshop for lunch and
WRG cheesecake. We like WRG work party leftover food. Ian M spotted us so we ‘volunteered’
to take a length of hose to the WRG working at Dudbridge. Lots of activity
going on there.
Then to finish off we did some more digging and a final
selfie. To be continued at some point
in the future.