Project 'DNF' - No.5 Refit
A very brief report this time. Given that we had repaired one of the fixing points for the side tanks the other week and added rubber 'bang' protectors down the sides, it seemed sensible to check that they would still drop into place and the securing bolts go through the holes.
We were able to sling the tanks from the boom and use it to raise each of the tanks enough to for them to slot in. The task verified that both sides fitted correctly, we'd not want to discover an alignment problem when splashing around in the water.